812WAB® isolates shale collapse on exploration well

WAB - Welltec Annular Barrirer - case story JMA181487

Well type

Gas / appraisal

Reservoir type

Sandstone

Isolation of shale collapse

Provided tangible DST results from producing zone

Open hole placement of wab

Isolated any potential for shale collapse

Wab application versatility enabled

Preferred well methodology

Operational focus ensured

All objectives met in this challenging application

Location

Malaysia

Background

A vertical carbonate exploration well in the Ginseng field, Petronas offshore Malaysia, was expecting heavy losses and possible shale formation collapse.

This was the client's first exploration well since the downturn. After installing the completion the client planned to do well testing before completing P&A of the well.

Solution

Welltec® offered a Welltec Annular Barrier (812WAB7.5:5) solution as a primary plan as part of a contingency liner to isolate total losses and support the formation from shale collapse above. The 812WAB was made up as part of the 7’’ contingency liner and expanded to 8-1/2’’ OH size.

As no losses were encountered. The WAB was installed to support the formation from shale collapse. The lower completion consisted of a 812WAB mounted on 4-1/2’’ base pipe was made up and x-over to the 7 in liner. The WAB & liner hanger was set simultaneously against the 3-1/2’’ pre-installed HPHT bridge plug.

Achievements

This was the second successful WAB installation for this IOC following on from the installation within a cemented mono-bore campaign. The WAB supported the formation from shale collapse allowing the successful evaluation of hydrocarbon potential via well testing. Zero Non-production time.

Due to well changes during drilling i.e. no losses, the setting of the WAB was constantly changing. This was of substantial benefit to the client, due to the versatility of the WAB and being able to set in open hole or cased hole.

II

The WAB’s application versatility, allows for adaptive changes in well design during milestone exploration well.

Welltec

Well schematics

1036X518 Jma181487 812Wab Isolates Shale Collapse On Exploration Wellpng

Products applied

WAB for Well Completion (Welltec Annular Barrier)

WAB® for Well Abandonment (Welltec® Annular Barrier)

Future-proof wells for CAPEX effective P&A

Similar cases