Patch setting depth
Total operation time
Two ½” punched holes isolated and sealed
Tubing ID reduction
When an operator in Southern Europe required a cost-effective solution to isolate two ½-inch punched holes in a 4-1/2” production tubing, a Welltec® Springblade Patch was deployed and set via wireline, then successfully pressure tested within a total operational time of 46.5 hours.
The solution provided a reliable seal with minimal impact on tubing inner diameter, enabling the operator to efficiently progress their well intervention program toward production from new intervals.
The successful outcome generated strong client interest in applying the technology in future operations.
Challenge
Production tubing remediation
Solution
Welltec® Springblade Patch
Location
Southern Europe
Conditions
Well type: Vertical oil producer kicking off to horizontal liner across lower reservoir
Max. temp: 82°
Max. pressure: 250 bar