transparent
transparent
transparent
transparent home Sitemap Green arrowContact us
Search for:   
transparent
transparent
transparent  » Services » Our Technologies » Well Tractor » Case Stories
transparent
transparent
transparent
transparent transparent transparent
  
  
  
  
  
  
  
  
  
  
transparent
transparent
transparent
transparent transparent transparent

Successful Open Hole Operation

 

November 2002

The open hole Well Tractor performed a successful MDT logging job in the Statfjord field in Norway. The well path was S-shaped above the reservoir section with a maximum inclination of 70º, which dropped to about 20º in the reservoir section.

The MDT tool was run in hole on wireline to about 8.5 ft MD RKB. At this point, the well reached an inclination of 69.4º. The Well Tractor was then powered up and tractored down to around 10.8 ft MD RKB across the part of the well where the inclination reached 70º. When the angle dropped, the Well Tractor was turned off and logging was completed on wireline. The pressure points were taken while running in hole on wireline; they reached a total of 18 points.

The benefits of the operation were obvious. Two days were saved compared to a TLC logging job; one day due to less time spent on the job and one day due to leaving out wipetrip after logging. Additionally, the risk of lost circulation was reduced, which increased the probability of a good cement job since the open hole is exposed for a shorter time.
 

Well Data

Total depth:             12,920 ft
Maximum deviation: 70º
Maximum dogleg:     7.89º/10 ft
Pressure points:       18

transparent
transparent
transparent
transparent
Welltec has an excellent track record of performance.

Read more about the value we have created for our clients here.

 

transparent

transparent
transparent
2008
Welltec® Performs World’s First Milling of Bridge Plugs on Wireline
Welltec is the first